Request For Proposals Saint Paul Small Boat Harbor Utilities Expansion Project

For Economic Development Administration Grant 07-79-07871

December 8, 2025 

Summary: The  City  of  Saint  Paul  will  receive  sealed  bids  for all work required for the Small Boat  Harbor Utilities Expansion project including demolition of the existing lift station and construction of a new lift station. Bids shall be on a stipulated lump sum basis.

To be considered, proposals must be received via email no later than January 23, 2026 no later than 2:00 pm Alaska Standard Time. Electronic proposals should be in a single PDF format and sent by email to pazavadil@stpaulak.com  with the subject line “Bid to RFP 25-03.”

If you have any questions concerning this request, please contact Jodi Plante
at (907) 321-7663 or jodi@akml.org

REQUEST FOR PROPOSAL SCHEDULE
Release of RFP:December 8, 2025
Questions & Clarification Deadline:December 30, 2025 at 5:00 pm AST
Pre-Bid Conference:

January 5, 2026 at 9:00 am AST

Join via Zoom meeting (clickable link to the meeting)
https://us02web.zoom.us/j/89801314743?pwd=BQCbIFYKaZUeUUIrHDbN67GzaGRfK6.1

Meeting ID: 898 0131 4743
Passcode: 768419

Questions Deadline:January 9, 2026
Proposals Due:January 23, 2026 by 2:00 pm AST
Public Opening of Bids:

January 26, 2026 at 1:00 pm AST

Bids will be publicly opened and read aloud on January 26, 2026 at 1:00 p.m. via Zoom:
https://us02web.zoom.us/j/89758100950?pwd=KqHHnTSuupgzfcB0XkW5jRskbnxm0T.1
Meeting ID: 897 5810 0950
Passcode: 014601

Review & Selection of Firm:February 5, 2026
Negotiation of Contract:February 19, 2026

Download the RFP

Register to receive notice when details of this RFP are updated.

Register as an Interested Vendor for this project 


Question and Answer section for RFP 25-03


 A: The engineers do not recommend steel due to the harsh and corrosive environment conditions on steel. That’s why timber has been specified. Traditional wood frame construction and the specified materials last longer in our harsh marine environment. You can prefab and deliver to Saint Paul Island via barges. The City will not consider alternative materials unless they can provide significant cost savings with the same longevity as what is specified in the plans. (Revised 12/30/25)

A: There is an aerial photograph on the first page of the drawing set.  You may also want to use Google Maps or Google Earth.  However, there is not much there to see.  You are better off taking a close look at the drawings, as they show everything necessary for the project.

A: Originally, no, the City had not scheduled a site visit or pre-bid conference. However, due to requests we have scheduled a pre-bid conference for Monday, January 5, 2026 at 9 am Alaska Standard Time.  See the proposal schedule for the Zoom meeting link.

A: The City has scheduled a pre-bid conference for Monday, January 5, 2026 at 9 am Alaska Standard Time.  See the proposal schedule for the Zoom meeting link.

A: No site-specific geotechnical investigation was completed. However, we contracted with a geophysical company to locate an old, buried seawall which is identified within the project area. The reports are included for reference.

A:  There are above grade landscaping boulders in the project vicinity which are intended to be relocated per the project . There are no known bedrock outcroppings to our knowledge in the project area. Please email the Project Manager additional information or a graphic.

A:  Yes, please proceed with the AIA documents containing a DRAFT watermark.

A: Specifications for materials include manufacturer’s warranty for hardware where a five year minimum is provided.  The period for correction of work for the entire Project in it’s entirety is one year after substantial completion. The warranties for specific products are in addition to Article 18 CORRECTION OF WORK.

A:  All easements have been acquired for the project.  This was a requirement from the grant funding agency, Economic Development Administration, prior to publishing the RFP.

A: The engineers do not recommend steel due to the harsh and corrosive environment conditions on steel. That’s why timber has been specified. Traditional wood frame construction and the specified materials last longer in our harsh marine environment. You can prefab and deliver to Saint Paul Island via barges. The City will not consider alternative materials unless they can provide significant cost savings with the same longevity as what is specified in the plans.

A:  Out swinging doors in the winds of St. Paul is not recommended as the door could get ripped off the hinges and has potential to injure workers.

A: The specified fiberglass box pads have a built-in vault and so they will be partially buried.

A: Install per manufacturer’s instructions.

A: The feeder the demoed transformer is connected to can be fed from two directions.  You will need to work with the local utility to isolate that section of the distribution system, and power is backfed on that feeder making backup generation unneeded.  The contractor will be given that current power distribution system 1-line during construction so they can ensure where lockout provision needs to be made during splice work.

A: Yes, the basis for design is the IEI Labs controller as called out on the drawings and functionality called out in the specifications.  The other key SCADA requirement is that the new equipment needs to be integrated into the SCADA and lift stations that are currently under construction and use this equipment.

A:  The RS poles that are in the plans come in 2 sections. We have used these in the past. We just use our Lull extended boom forklift to attach the second section and hang the mounts light. It has a 50’ reach. To dig the holes, we have used either our New Holland backhoe or Cat 309 excavator. The excavator has an auger attachment for it. 


 

Answer has been edited since originally posted.